Continuing the start of this project:
 |
Pouring the basement floor slab on top of the foam insulation and the “In-floor” heating tubes. |
 |
Going up from there with the ICF forms |
 |
…they stack up like life sized “Legos”… |
 |
Here the insulated concrete form walls are completed and have been filled with concrete. Ready for a subfloor to be built. |
 |
Floor trusses have been put in place on top of the basement/foundation walls. |
 |
…and the sheathing is finished. This is the main floor of the house… |
|
|
The house is now ready for the timber frame and wall structure.